Our Process

At Venyainfra, every project is executed through a structured, transparent, and quality-driven process. From initial planning to final handover, each stage is carefully planned, supervised, and delivered by our in-house skilled teams. Our process ensures consistency in workmanship, adherence to timelines, and uncompromised quality at every phase of construction.

Planning & Design (Weeks 1-4)

Activities:

  • Design finalization and client approval.

  • GHMC/Municipal approvals and NOCs.

  • Soil testing and site assessment.

  • Material planning and procurement.

  • Team mobilisation and site setup

Deliverables:

Approved design, permission documents, bill of materials.

Plumbing, Electrical & MEP (Months 6-8)

Activities:

  • Underground plumbing and drainage systems (expert plumbers with high-rise experience).

  • Water supply line installation with premium fixtures.

  • Electrical conduit roughing and cabling (licensed electricians with high-rise background).

  • Sanitary fitting positioning and installation.

  • Mechanical system setup.

Quality Checkpoints:

Plumbing pressure tests, electrical safety verification, MEP coordination, fixture quality inspection.

Deliverables:

Functional plumbing and electrical systems.

Final Handover (Month 12)

Activities:

  • Final quality audit and snag list clearance.

  • Deep cleaning and site preparation.

  • Client walkthrough and feedback.

  • Rectification (if any).

  • Project handover.

Quality Checkpoints:

  • Final quality compliance verification.

  • Functional testing of all services.

  • Documentation completeness check.

Deliverables:

  • Completed turnkey home.

  • Handover documents.

  • Warranty and service information.

Foundation & Structure (Months 2-5)

Activities:

  • Site leveling and boundary demarcation.

  • Foundation excavation and concrete work.

  • RCC column and beam structure.

  • Brick masonry and structural completion.

  • BIS inspection for structural integrity.

Quality Checkpoints:

Foundation strength testing, concrete mix verification, structural safety inspections

Deliverables:

Completed structure.

Finishing (Months 9-11)

Activities:

  • Wall plastering and leveling.

  • Professional painting (premium painters with high-rise project experience).

  • Tiling and flooring (premium finishes).

  • Kitchen and bathroom customization.

  • Door and window installation.

  • Final electrical and plumbing connections.

Quality Checkpoints:

Surface flatness, tile alignment, paint finish uniformity, electrical load testing, water pressure verification, finish quality.

Deliverables:

Fully finished house ready for occupancy.

OUR COMMITMENT

  • In-house skilled execution teams.

  • Dedicated supervision at every stage.

  • Transparent processes and communication.

  • Superior finishing quality.

  • Timely delivery and dependable after-sales support.

bottom of page